Welcome to a special series on the acquisition talk podcast that gives you an audiobook tour of my research project titled, Programmed to Fail: The Rise of Central Planning in Defense Acquisition 1945 to 1975. I’m Eric Lofgren of the Baroni Center for Government Contracting at George Mason University. You can find this book for free and over 1,300 blog posts on my website, AcquisitionTalk.com.
Monolithic program budgets have led to monolithic contracts that have thwarted technical goals. However, if DoD can reform its budgeting process, it can also unpack system requirements and modularize contracts alongside technically separable components. This is important because different elements of a system have different development cycle times. For example, advances in material sciences and infrastructure move slowly, perhaps on the order of five to ten years or more. Aided by Moore’s law, electronics can cycle through new models every couple of years. Software is even faster, capable of deploying new updates potentially every day. Defense officials cannot afford to slow down entire weapon systems to the slowest common denominator, and must instead move in asynchronous times to maximize technological progress.
In this episode of Programmed to Fail, the relationship between the budgeting and contracting processes will be made. It finds that the premature of defining entire program lifecycles also makes its way into the contract, which constrains the adaptive learning process. A properly functioning contract process with industry requires a flexible budgeting process within government.
This podcast was produced by Eric Lofgren. You can follow me on Twitter @AcqTalk and find more information at AcquisitionTalk.com
Monolithic program budgets have led to monolithic contracts that have thwarted technical goals. However, if DoD can reform its budgeting process, it can also unpack system requirements and modularize contracts alongside technically separable components. This is important because different elements of a system have different development cycle times. For example, advances in material sciences and infrastructure move slowly, perhaps on the order of five to ten years or more. Aided by Moore’s law, electronics can cycle through new models every couple of years. Software is even faster, capable of deploying new updates potentially every day. Defense officials cannot afford to slow down entire weapon systems to the slowest common denominator, and must instead move in asynchronous times to maximize technological progress.
In this episode of Programmed to Fail, the relationship between the budgeting and contracting processes will be made. It finds that the premature of defining entire program lifecycles also makes its way into the contract, which constrains the adaptive learning process. A properly functioning contract process with industry requires a flexible budgeting process within government.
This podcast was produced by Eric Lofgren. You can follow me on Twitter @AcqTalk and find more information at AcquisitionTalk.com
ingilizce
Amerika Birleşik Devletleri
TRANSKRİPT 🔗
Are you the producer of this podcast?
Add a podcast transcript
Need Audio-to-Text?
Transcribe with Listen411 in Just 60 Seconds
SON BÖLÜMLERİ ARA
Acquisition Talk için geçmiş bölümleri ara.
BU PODCAST'IN DİĞER BÖLÜMLERİ
Balloon bloodlust, the epic military history of balloons, the fate of US-China relations, and how balloon expertise can help you on Hinge
What on Earth is a Chinese spy balloon doing over the US? To discuss, we have William “Balloon Guy” Kim of The Marathon Initiative, Eric Lofgren of Acquisition T…
Welcome to a special series on the acquisition talk podcast that gives you an audiobook tour of my research project titled, Programmed to Fail: The Rise of Central Planning in Defense Acquisition 1945 to 1975. I’m Eric Lofgren of the Baroni Center for Government Contracting at George Mason Universi…
Welcome to a special series on the acquisition talk podcast that gives you an audiobook tour of my research project titled, Programmed to Fail: The Rise of Central Planning in Defense Acquisition 1945 to 1975. I’m Eric Lofgren of the Baroni Center for Government Contracting at George Mason Universi…
I was pleased to have Pete Newell back on the Acquisition Talk podcast to discuss the urgency of getting innovative defense prototypes into the field and working with partner nations. Pete is founder and CEO of BMNT Inc., a global technology advisory firm, co-founder of Hacking 4 Defense, and a ret…
Welcome to a special series on the acquisition talk podcast that gives you an audiobook tour of my research project titled, Programmed to Fail: The Rise of Central Planning in Defense Acquisition 1945 to 1975. I’m Eric Lofgren of the Baroni Center for Government Contracting at George Mason Universi…
Feragatname: Bu sayfaya yerleştirilmiş podcast ve sanat eserleri, sahibinin mülkiyetinde olan ve Listen Notes, Inc.'e bağlı olmayan veya tarafından onaylanmayan Eric Lofgren'e aittir.
DÜZENLE
Podcast veritabanını güncel tutmaya yardımcı olduğunuz için teşekkür ederiz.