In this episode, I examine the U.S. Department of Energy’s $1.9 billion SPARK initiative funding 31 grid-improvement projects across 26 states, and explain how Alternative Transmission Technologies (ATTs) and Grid Enhancing Technologies (GETs) can unlock significant grid capacity without waiting decades for new transmission lines.
Here are the key topics and technologies I break down in today's video:
- The Transmission Permitting Bottleneck: Why building new transmission lines takes over a decade—highlighting the 3,600 MW SunZia wind transmission line, which took 17 years from permitting to first power—and why a recent study showed only ~15 miles of high-voltage transmission built in the U.S. between 2022 and 2024.
- The DOE SPARK Initiative: How $1.9 billion in federal funding (catalyzing an additional $3.35 billion in recipient cost-sharing) aims to make 23 gigawatts (23,000 MW) of additional transmission capability available across existing rights-of-way.
- FERC Regulatory Mandates (Order 2023 & Order 1920): How FERC Order 1920 shifted from merely encouraging grid operators to requiring them to evaluate and document cost-effective GETs before receiving approval to build new interstate transmission.
- Advanced Re-conductoring: Replacing old ACSR (aluminum conductor steel reinforced) wires with lighter, trapezoidal composite-core conductors that can double line capacity on existing towers at less than half the cost of new lines.
- Dynamic Line Ratings (DLR): How sensors and software monitor real-time wind and temperature conditions—acting like "an MRI on your wires"—to allow significantly higher power flows during cooler or windier periods.
- Topology Flow Optimization: How grid operators like MISO and SPP use software to switch breakers and redirect electron traffic around bottlenecks—acting as "Waze for the power grid" to reduce congestion costs.
- Advanced Power Flow Controls: Adjusting line characteristics and injecting reactive power to push electricity off overloaded lines onto underutilized capacity.
If you find this deep dive into grid optimization helpful, please like, subscribe, and leave a comment with your thoughts on how your local grid operator is handling transmission constraints.
🎙️ About Energy Future: Powering Tomorrow’s Cleaner World
Hosted by Peter Kelly-Detwiler, Energy Future explores the trends, technologies, and policies driving the global clean-energy transition — from the U.S. grid and renewable markets to advanced nuclear, fusion, and EV innovation.
💡 Stay Connected
Subscribe wherever you listen — including Spotify, Apple Podcasts, Amazon Music, and YouTube.
🌎 Learn More
Visit peterkellydetwiler.com
for weekly market insights, in-depth articles, and energy analysis.
노트보기 🔗
전사 🔗
00:00:02.560 --> 00:00:04.080
In late September, the U.S.
00:00:04.160 --> 00:00:14.160
Department of Energy's Office of Electricity announced it would help fund 31 grid improvement projects across 26 states as part of the department's SPARC initiative.
00:00:14.400 --> 00:00:17.039
This acronym really needs some help, by the way.
00:00:17.280 --> 00:00:23.120
Speed to power through accelerated reconductoring and other key advanced transmission technology upgrades.
00:00:23.359 --> 00:00:26.800
Shouldn't that be SPARCO KATU or something like that?
00:00:26.960 --> 00:00:27.920
Who comes up with these?
00:00:28.079 --> 00:00:29.839
Has the deep state run amok?
00:00:30.320 --> 00:00:45.200
At any rate, these are projects that don't involve creating whole new transmission rights of way and building out entirely new lines, but instead they're focused on enhancing the transmission system we have, flowing more power across the existing system with the help of new technologies.
00:00:45.439 --> 00:00:52.799
That matters a great deal because this country's way behind in creating the transmission capability we need to keep up with growing demand.
00:00:52.960 --> 00:00:57.200
Without permitting reform, this whole area is quite frankly a mess.
00:00:57.439 --> 00:01:01.840
It can take well over a decade to acquire the permits to construct new lines.
00:01:02.079 --> 00:01:10.560
As a recent egregious example, take the Sun Zia line, which connects 3,600 megawatts of New Mexico wind to Arizona and eventually California.
00:01:10.719 --> 00:01:19.040
That took 17 years to permit and build, with numerous state and federal agencies involved finally flowing first power this summer.
00:01:19.359 --> 00:01:24.480
Transmission lines generally involve condemning private property rights through eminent domain.
00:01:24.640 --> 00:01:31.519
The pitting of the general good, the collective good, against the rights of the individual landowner, well, that never goes over very well in this country.
00:01:31.680 --> 00:01:34.640
None of us would want new lines running through our neighborhoods.
00:01:34.799 --> 00:01:36.719
So we need to do more with what we have.
00:01:36.959 --> 00:01:49.120
The sad reality, as pointed out by a recent grid strategy study, showed that only about 1,500 miles of high voltage transmission lines have been built over the three-year period from 2022 to 2024.
00:01:49.519 --> 00:01:51.200
We need far more than that.
00:01:51.439 --> 00:02:09.120
To remedy this issue, the DOE will spend$1.9 billion, an amount that will catalyze an additional$3.35 billion in recipient cost fund sharing in order to make over 23,000 megawatts, 23 gigawatts, of additional transmission capability available.
00:02:09.360 --> 00:02:13.199
A number of technologies will be deployed to enhance this transmission.
00:02:13.520 --> 00:02:33.680
Project developers are anticipated to rebuild or reconduct over 1,500 miles of lines, and in addition, grant recipients will also deploy grid-enhancing technologies, so-called GETs, non-wire technologies such as dynamic line ratings, topology flow optimization, and advanced power flow controls across nearly 21,000 miles of lines.
00:02:33.840 --> 00:02:42.400
Taken together, the DOE has estimated that these types of so-called alternative transmission technologies have the potential to expand U.S.
00:02:42.479 --> 00:02:46.479
transmission capability by somewhere between 40 and 100 gigawatts.
00:02:46.639 --> 00:02:52.560
So the 23 gigawatts of improvements here would be a very good start if, in fact, it all comes to fruition.
00:02:52.800 --> 00:02:59.199
By the way, the Federal Energy Regulatory Commission has been coaxing grid operators to do this sort of thing for some time.
00:02:59.439 --> 00:03:06.479
In 2023, with FERC Order 2023, it encouraged them to consider such alternatives, but just encourage them.
00:03:06.639 --> 00:03:29.680
More recently, in Order 1920, put out in 2024, the FERC then told grid operators they had to evaluate and document whether cost-effective alternative transmission technologies, specifically GETS, the grid enhancing technologies, could resolve identified system needs before those companies would ever receive approval to proceed on building new transmission lines interstate.
00:03:30.080 --> 00:03:36.240
Let's take each of these alternative transmission technologies in turn and explain what they are and how they work.
00:03:36.639 --> 00:03:38.319
First, reconductoring.
00:03:38.479 --> 00:03:42.080
This is the process of hanging more efficient wires on existing lines.
00:03:42.319 --> 00:03:55.599
Most existing high voltage transmission technology today employs an old technology called alternative conductor steel reinforced or ACSR lines, in which aluminum strands surround a heavy steel core.
00:03:55.759 --> 00:04:00.560
The new advanced conductors employ smaller, composite-based and lighter cores.
00:04:01.120 --> 00:04:07.120
They allow for higher temperatures and the packing of more conductive aluminum in the same equivalent diameter.
00:04:07.199 --> 00:04:11.840
They include a trapezoidal design so there's no empty space between the strands of wires.
00:04:12.000 --> 00:04:14.400
This means they carry up to 2x the power.
00:04:14.639 --> 00:04:25.040
The main benefit then is they use existing transmission towers in most instances, and the rights of ways already exist, so no land acquisition and limited permitting processes.
00:04:25.360 --> 00:04:31.600
A really good study of the economic benefits of reconductoring came out of the Berkeley Haas School a few years ago.
00:04:31.759 --> 00:04:47.439
And that study summarized reconductoring as follows: quote, we find that large-scale reconductoring with advanced composite core conductors can cost-effectively double transmission capacity within existing right-of-way with limited additional permitting, unquote.
00:04:47.759 --> 00:04:49.759
This reconductoring tech's not new.
00:04:49.920 --> 00:04:53.680
Tens of thousands of miles of lines are used around the world.
00:04:53.839 --> 00:04:58.639
And even here, AEP and others have been deploying this technology for a while.
00:04:58.800 --> 00:05:02.160
And there are multiple manufacturers in the US and abroad as well.
00:05:02.399 --> 00:05:03.839
So that's not the issue.
00:05:04.079 --> 00:05:11.439
The bottom line, though, advanced reconductoring can double the capacity at less than half the cost of new lines in a fraction of the time.
00:05:11.680 --> 00:05:18.000
Okay, now let's move on to the so-called GETS, the grid enhancing technologies that don't involve the string of new wires.
00:05:18.240 --> 00:05:24.319
At most, they include sensors, software, some limited equipment, and a lot of IT.
00:05:24.560 --> 00:05:26.560
Let's start with dynamic line ratings.
00:05:26.720 --> 00:05:30.079
Today, transmission lines are assigned static ratings.
00:05:30.319 --> 00:05:36.079
They're meant to ensure that the lines can deliver X amount of energy during the hottest and calmest periods of the year.
00:05:36.319 --> 00:05:38.560
Transmission lines don't deal well with heat.
00:05:38.720 --> 00:05:48.160
The process of moving electricity through lines involves the creation of heat, and the more current you move through the wires, the more resistance you get with this associated heat.
00:05:48.319 --> 00:05:52.720
And if you double the current moving through the line, you quadruple the heat generated.
00:05:52.959 --> 00:06:00.240
But here's the thing: the same way that colder temps chill us down, temperatures can do the same thing to transmission lines.
00:06:00.319 --> 00:06:01.920
And wind is even more critical.
00:06:02.160 --> 00:06:05.040
We all know about wind chill factor in winter weather.
00:06:05.199 --> 00:06:08.639
Wind is very effective at wicking away transmission line heat.
00:06:08.879 --> 00:06:18.319
So DLRs, using a combination of sensors and software, create situational awareness with respect to the actual conditions you're moving your power through those lines in.
00:06:18.480 --> 00:06:21.279
It's like having an MRI on your wires.
00:06:21.519 --> 00:06:33.519
A study by Energy Holding Company AES demonstrated that on the coldest and windiest days, one can move up to or more than twice the juice through the same wires in significant average quantities across the entire winter.
00:06:33.759 --> 00:06:39.519
Spring and fall, you can also move a lot more, and even in the summer, except for those hottest and stillest days.
00:06:39.759 --> 00:06:45.360
And some of those sensors, by the way, they can be flown up and attached to the wires using drones.
00:06:45.839 --> 00:06:48.079
But what about topology flow optimization?
00:06:48.240 --> 00:06:49.439
What's going on there?
00:06:49.839 --> 00:06:52.959
Think about that like ways for the power grid.
00:06:53.199 --> 00:06:59.519
Normally, power flows on a path of least resistance, and frequently it gets bottled up by transmission constraints.
00:06:59.600 --> 00:07:07.600
So you can't always get the cheapest power to the load pockets, and you have to call for more expensive power, which creates congestion costs.
00:07:07.759 --> 00:07:20.800
But if you open up some breakers on the grid and close others, you can create detours and redirect electron traffic onto different transmission paths, so lower cost power can get to load pockets that would previously have been inaccessible.
00:07:21.120 --> 00:07:29.439
SPP and MISO, those two grids, both already use this tech, with SPP just gaining approval from the FERC this past month.
00:07:29.680 --> 00:07:32.480
Finally, there are advanced power flow controls.
00:07:32.639 --> 00:07:37.519
These adjust the characteristics of transmission lines so that power moves differently through the system.
00:07:37.680 --> 00:07:46.160
One can inject reactive power, for example, onto the system to shift more power from one overloaded line to another that still has ample capacity.
00:07:46.720 --> 00:07:53.439
In summary, the DOE grants are meant to stimulate something that frankly should have happened a long time ago in this country.
00:07:53.600 --> 00:07:59.680
The deployment of technologies and processes that will allow us to utilize our existing system far more efficiently.
00:07:59.920 --> 00:08:08.560
We're still going to have to build new lines, but in the meantime, this is a step closer to being smarter and adapting the infrastructure we already have.
00:08:08.800 --> 00:08:11.439
Well, thanks for watching, and we'll see you again soon.