Cyprium Metals executive chairman Matt Fifield talked with Proactive about key commissioning milestones at the Nifty Copper Complex in Western Australia, as the company advances heap leach operations and prepares for first copper cathode production.
Fifield explained that commissioning activities are progressing across the heap leach operation, while pre-commissioning work on the solvent extraction and electrowinning (SXEW) plant is approaching completion.
The company has achieved targeted injection flow rates through its direct injection leaching process, building on more than a year of trials and testing to establish the technology's suitability for the existing Nifty heaps.
Fifield said early commissioning results had been particularly encouraging, with copper recovery responding quickly to acid injection and copper-to-acid ratios performing better than initially anticipated.
The interview also covered grade control drilling, which has reconciled within approximately 5% of the existing mineral resource block model, strengthening confidence in the company's production assumptions.
Cyprium Metals has established 212 production and monitoring wells, providing access to approximately 1.7 million tonnes of material and supporting an estimated six to eight months of planned production under conservative recovery assumptions.
Fifield also outlined the remaining milestones ahead of wet commissioning, including the installation of programmable logic controller (PLC) controls and energisation of the SXEW plant, following the introduction of high-voltage power to the plant infrastructure.
With heap leach operations ramping up and commissioning milestones being achieved, Cyprium Metals is progressing towards its next stage of copper production at Nifty.
Watch the full interview to hear Matt Fifield discuss the latest commissioning achievements, copper recovery performance and upcoming operational milestones.
For more interviews and updates from ASX-listed companies, visit Proactive's YouTube channel. Remember to like this video, subscribe to the channel and enable notifications so you don't miss future updates.
#ASXCYM #CopperProduction #MiningNews #CopperProjects #WesternAustralia #HeapLeaching #SXEW #CriticalMinerals #AustralianMining #ProactiveInvestors
Fifield explained that commissioning activities are progressing across the heap leach operation, while pre-commissioning work on the solvent extraction and electrowinning (SXEW) plant is approaching completion.
The company has achieved targeted injection flow rates through its direct injection leaching process, building on more than a year of trials and testing to establish the technology's suitability for the existing Nifty heaps.
Fifield said early commissioning results had been particularly encouraging, with copper recovery responding quickly to acid injection and copper-to-acid ratios performing better than initially anticipated.
The interview also covered grade control drilling, which has reconciled within approximately 5% of the existing mineral resource block model, strengthening confidence in the company's production assumptions.
Cyprium Metals has established 212 production and monitoring wells, providing access to approximately 1.7 million tonnes of material and supporting an estimated six to eight months of planned production under conservative recovery assumptions.
Fifield also outlined the remaining milestones ahead of wet commissioning, including the installation of programmable logic controller (PLC) controls and energisation of the SXEW plant, following the introduction of high-voltage power to the plant infrastructure.
With heap leach operations ramping up and commissioning milestones being achieved, Cyprium Metals is progressing towards its next stage of copper production at Nifty.
Watch the full interview to hear Matt Fifield discuss the latest commissioning achievements, copper recovery performance and upcoming operational milestones.
For more interviews and updates from ASX-listed companies, visit Proactive's YouTube channel. Remember to like this video, subscribe to the channel and enable notifications so you don't miss future updates.
#ASXCYM #CopperProduction #MiningNews #CopperProjects #WesternAustralia #HeapLeaching #SXEW #CriticalMinerals #AustralianMining #ProactiveInvestors
Inglese
Stati Uniti
TRASCRIZIONE 🔗
Are you the producer of this podcast?
Add a podcast transcript
Need Audio-to-Text?
Transcribe with Listen411 in Just 60 Seconds
CERCA TRA GLI EPISODI PASSATI
Cerca gli episodi passati di Proactive - Interviews for investors.
ALTRI EPISODI IN QUESTO PODCAST
Krait Critical Minerals Corp CEO Oscar Mendoza joined Steve Darling from Proactive to discuss the company's expanding US antimony portfolio, its recent acquisition of an antimony asset in Humboldt County, Nevada, and its strategy of acquiring historically producing critical mineral properties acros…
VettaFi Head of Energy Research Stacey Morris joined Steve Darling from Proactive to discuss how Middle East energy supply disruptions could create long-term opportunities for North American energy producers and midstream infrastructure companies.
Morris explained that the US and Canada could beco…
IP Group PLC (LSE:IPO) CEO Greg Smith joined Steve Darling from Proactive to discuss new data showing that investment in UK university spinouts reached £1.56 billion in the first half of 2026, marking the second-highest half-year total recorded over the past decade.
The figures come from a new rep…
Custom Health CEO Shane Bishop joined Steve Darling from to discuss early results from the company’s ongoing commercial program with BKC Pain Specialists & Regenerative Medicine Clinic in Ohio, highlighting how its integrated medication management model is supporting patients living with chroni…
Pantheon Resources PLC (AIM:PANR, OTCQX:PTHRF) newly appointed CEO Dave Wilkins and former CEO Max Easley joined Steve Darling from Proactive to discuss the leadership transition, as Wilkins takes over at the helm of the company, effective immediately. Easley has taken another senior executive role…
Dichiarazione di non responsabilità: Il podcast e la grafica incorporati in questa pagina provengono da Proactive, che è di proprietà del suo proprietario e non è affiliato o approvato da Listen Notes, Inc.
MODIFICA
Grazie, ci hai aiutato a mantenere aggiornato il database dei podcast.