Welcome to another episode of the Construction Law Shortcast series where we'll be deconstructing fundamental principles of English construction law.
00:00:19.839 --> 00:00:22.160
All in just five minutes or thereabouts.
00:00:22.160 --> 00:00:28.399
I'm Noe Minamikata from the London Construction and Infrastructure Disputes Team here at HSF Kramer.
00:00:29.199 --> 00:00:36.079
And I'm Xavier Milne, also from HSF Kramer's London Construction and Infrastructure Disputes Team.
00:00:36.640 --> 00:00:43.200
In this episode, we'll be focusing on three related concepts which frequently come up in construction disputes.
00:00:43.200 --> 00:00:46.399
Delay, float, and extensions of time.
00:00:46.399 --> 00:00:52.719
To start us off, Xavier, can you walk us through the concept of delay and what it means in a construction context?
00:00:53.520 --> 00:00:54.000
Sure.
00:00:54.000 --> 00:01:02.880
Under most construction contracts, the contractor needs to complete the works by a fixed date specified in the contract.
00:01:02.880 --> 00:01:07.120
This is often referred to as a scheduled completion date.
00:01:07.120 --> 00:01:15.680
When we talk about delay in a construction context, what we usually mean is delay that impacts the scheduled completion date.
00:01:15.680 --> 00:01:22.560
This is known as critical delay, because it involves delay to the critical path to completion.
00:01:23.280 --> 00:01:32.400
So if the contractor's progress is delayed but the scheduled completion date isn't impacted, this doesn't qualify as critical delay, is that right?
00:01:32.879 --> 00:01:33.760
That's right.
00:01:33.760 --> 00:01:41.359
Most construction contracts also contain, or should contain, a mechanism for addressing critical delay.
00:01:41.359 --> 00:01:47.280
This includes allocating the risk of delay to either the contractor or the employer.
00:01:47.760 --> 00:01:52.159
Okay, and how do construction contracts tend to allocate risk?
00:01:52.719 --> 00:01:54.799
That really depends on the contract.
00:01:54.799 --> 00:02:03.920
But typically, the contractor assumes the risk of delay if it was caused by the contractor or a contractor risk event.
00:02:03.920 --> 00:02:12.240
Likewise, the employer assumes the risk of delay if it was caused by the employer or an employer risk event.
00:02:12.800 --> 00:02:14.240
That seems very sensible.
00:02:14.240 --> 00:02:19.599
And we mentioned at the outset that delay is related to the concept of float.
00:02:19.599 --> 00:02:22.159
Can you explain what we mean here by float?
00:02:22.800 --> 00:02:35.280
When we talk about float, we usually mean the amount of time that an activity can be delayed without impacting activities that immediately follow or the scheduled completion date.
00:02:35.280 --> 00:02:42.000
It's a form of contingency that's built into the program to allow for unforeseen issues.
00:02:42.479 --> 00:02:48.479
So what happens where a project is delayed but the delay can't be absorbed in that float?
00:02:49.360 --> 00:02:58.400
If the employer or an employer risk event caused the delay, the contractor can usually claim an extension of time under the contract.
00:02:58.400 --> 00:03:09.840
But if it was the contractor or a contractor risk event that caused the delay, the contractor usually won't be able to be entitled to an extension of time.
00:03:10.719 --> 00:03:18.319
And are there any instances where delay is caused by both the contractor and the employer in almost equal measure?
00:03:18.719 --> 00:03:20.879
Yes, but it's rare.
00:03:20.879 --> 00:03:24.960
This scenario is what we call concurrent delay.
00:03:24.960 --> 00:03:37.439
There's some debate around the precise requirements, but it's often said that for concurrent delay to exist, each event has to be an effective cause of delay to completion.
00:03:37.439 --> 00:03:44.800
It rarely occurs in practice, but when it does, it can present legal and factual challenges.
00:03:44.800 --> 00:03:50.639
Some construction contracts specifically address the risk of concurrent delay.
00:03:50.639 --> 00:04:03.199
But where the contract is silent, the general English law rule is that the contractor is entitled to an extension of time but no loss and expense claim.
00:04:03.199 --> 00:04:19.439
An extension of time usually refers to an adjustment to the scheduled completion date to reflect the period of delay.
00:04:19.439 --> 00:04:25.439
That's critical delay caused by the employer or an employer risk event.
00:04:25.439 --> 00:04:34.720
Where a contractor is entitled to an extension of time, it might also be entitled to claim loss and expense.
00:04:34.720 --> 00:04:40.560
Although this isn't always the case and will depend on contract terms.
00:04:41.120 --> 00:04:43.759
And that's a key point to remember, isn't it?
00:04:43.759 --> 00:04:52.000
Are there any other points that parties should be alive to when claiming an extension of time or assessing an extension of time claim?
00:04:52.480 --> 00:04:53.279
There are.
00:04:53.279 --> 00:05:26.800
Sure.
00:05:26.800 --> 00:05:40.319
So to sum up, I'd say the key points are when we talk about delay, what we mean is critical delay that can't be absorbed by any float and impacts the scheduled completion date.
00:05:40.319 --> 00:05:55.839
Which party bears the risk of delay depends on the cause, and finally, if a contractor considers it is entitled to an extension of time, it needs to properly follow the contractual process for making a claim.
00:05:55.839 --> 00:06:03.759
Likewise, an employer assessing a contractor's claim should check that it has strictly complied with the contractual process.
00:06:04.240 --> 00:06:10.879
Thanks, Evia, and that brings us to the end of this episode of the Construction Law Shortcast series.
00:06:10.879 --> 00:06:17.920
Thanks for listening, and please join us in our next episode where we'll be discussing the concept of disruption.