Welcome to the Montgomery County Department of Permitting Services podcast.
00:00:14.400 --> 00:00:16.480
I'm Gail Lucas, your host.
00:00:16.480 --> 00:00:21.120
I'm also the division chief for the Customer Support and Outreach Division.
00:00:21.120 --> 00:00:24.719
Joining us on the podcast today is Richard Stroud.
00:00:24.719 --> 00:00:33.759
Richard is a residential plan reviewer, and our topic today is demolition, knocking stuff down.
00:00:33.759 --> 00:00:41.840
But before we start talking about breaking stuff up, Richard, why don't you tell our listeners what you do, what a residential plan reviewer does.
00:00:42.240 --> 00:00:42.399
Sure.
00:00:42.399 --> 00:00:43.200
Hi Gail.
00:00:43.200 --> 00:00:44.560
Thanks for having me.
00:00:44.560 --> 00:00:45.679
It's great to be here.
00:00:45.679 --> 00:00:50.000
We take a look at your plans.
00:00:50.000 --> 00:00:51.759
You have a project in mind.
00:00:51.759 --> 00:00:54.479
You bring us a set of plans.
00:00:54.479 --> 00:01:00.240
We take a look at it, make sure that it meets the residential code requirements.
00:01:00.240 --> 00:01:05.599
And that would be the 2021 International Residential Code.
00:01:05.920 --> 00:01:06.239
Okay.
00:01:06.799 --> 00:01:07.120
Okay.
00:01:07.120 --> 00:01:16.159
So we take a look at that, see that it meets plan review requirements and meets code, and we either approve it or we send it back for corrections.
00:01:16.560 --> 00:01:16.879
Okay.
00:01:16.879 --> 00:01:20.799
Our topic today, as I said, is about demolition.
00:01:20.799 --> 00:01:23.760
It's about knocking houses down.
00:01:23.760 --> 00:01:29.359
And when we think about demolition, typical person thinks about demolition, that means we're taking it all the way down.
00:01:29.359 --> 00:01:34.560
But recently there was a change to the law with respect to demolition.
00:01:34.560 --> 00:01:40.079
So even if you're partially taking a house down, then you may need a demolition permit.
00:01:40.079 --> 00:01:41.840
Can you talk a little bit about that change?
00:01:42.239 --> 00:01:42.560
Sure.
00:01:42.560 --> 00:02:00.959
So what we've um what we've done is we saw the need to actually refine and define the you know the definition of demolition so that it's more specific and we actually put limits on it.
00:02:00.959 --> 00:02:14.639
So the limit is 67% of the house must, if you are demolishing more than 67%, okay, um, then you need a demolition permit.
00:02:14.800 --> 00:02:15.120
Okay?
00:02:15.520 --> 00:02:20.479
Up to that point you can use a addition alteration permit.
00:02:20.879 --> 00:02:21.199
Okay.
00:02:21.199 --> 00:02:28.080
So if I'm taking my house 100% down, it's a demolition, it requires a demolition permit.
00:02:28.080 --> 00:02:38.800
But if I'm leaving part of my house and up to 67% of my house is demolished, then it becomes necessary for me to get a demolition permit.
00:02:39.039 --> 00:02:39.360
Yes.
00:02:39.599 --> 00:02:41.199
How do you treat the house at that point?
00:02:41.199 --> 00:02:43.280
What is the house considered then?
00:02:43.280 --> 00:02:48.719
As a uh it's it's no longer an alteration or an addition.
00:02:48.719 --> 00:02:49.280
What is it?
00:02:49.599 --> 00:02:50.479
It's it's a new home.
00:02:50.479 --> 00:02:50.960
Okay.
00:02:50.960 --> 00:02:51.360
Okay.
00:02:51.360 --> 00:02:54.000
We view it as a new home at that point.
00:02:54.000 --> 00:03:11.199
So um with a new home, um, as with well, even in the addition alteration process, anything that you are adding or altering must meet code, minimum code, but with the new home, it must um have sprinklers for number one.
00:03:11.199 --> 00:03:14.400
Um it must meet all of the new energy requirements.
00:03:14.400 --> 00:03:15.039
Okay.
00:03:15.039 --> 00:03:15.520
Okay.
00:03:15.520 --> 00:03:24.639
Um, so it's regardless of if you're leaving that 33%, we're viewing that 30 33 percent as a new home.
00:03:24.960 --> 00:03:25.280
Okay.
00:03:25.520 --> 00:03:25.840
Okay?
00:03:25.840 --> 00:03:28.800
And and and that even comes to the foundation.
00:03:29.199 --> 00:03:29.439
Okay.
00:03:30.000 --> 00:03:34.479
A new home is required to have um waterproofing and drainage.
00:03:34.479 --> 00:03:34.960
Okay.
00:03:34.960 --> 00:03:35.280
Okay.
00:03:35.280 --> 00:03:45.599
If you're leaving that 60 uh 33 percent, excuse me, I want that um remaining portion to be properly waterproofed and properly drained.
00:03:45.599 --> 00:03:46.159
Yes.
00:03:46.159 --> 00:03:46.560
Okay.
00:03:46.560 --> 00:03:48.560
You don't get an exemption for that.
00:03:48.960 --> 00:03:52.080
Explain to our listeners how you calculate that 67%.
00:03:52.080 --> 00:03:56.400
How do I how do I know when I've hit it, or how do you know when I've hit it?
00:03:56.719 --> 00:04:02.639
It is a linear measurement taken on the exterior walls of the living space.
00:04:02.639 --> 00:04:03.439
All right.
00:04:03.439 --> 00:04:14.400
So a garage is not considered living space, so we're not necessarily counting the garage, but you know, room space over the garage may be living space, okay.
00:04:14.400 --> 00:04:14.639
Okay.
00:04:14.639 --> 00:04:16.879
If the garage is underground in the basement.
00:04:17.040 --> 00:04:17.199
Okay.
00:04:17.519 --> 00:04:18.399
Sometimes they are.
00:04:18.399 --> 00:04:22.959
Um, so it's a 67% linear measurement of exterior walls.
00:04:23.279 --> 00:04:23.519
Okay.
00:04:25.120 --> 00:04:30.720
And any portion of that wall between the corners that is demolished, that's included as well.
00:04:30.959 --> 00:04:31.279
Okay.
00:04:31.439 --> 00:04:31.680
Okay.
00:04:31.680 --> 00:04:41.680
So if you have a 100 square linear foot wall and um 50 feet of that in between the corners is going to be demolished.
00:04:41.680 --> 00:04:44.079
Then that counts in the county counts as well.
00:04:44.879 --> 00:04:49.839
So, with that, all of the requirements of a demolition permit kick in.
Load full transcript
00:04:49.839 --> 00:04:54.639
That means I need to have rodent inspection and rodent treatment if necessary.
00:04:54.639 --> 00:04:55.279
Yes.
00:04:55.279 --> 00:05:00.160
I need to have asbestos abatement if my home has asbestos.
00:05:00.160 --> 00:05:06.879
And most importantly, I need to pay a demolition bond to Montgomery County.
00:05:06.879 --> 00:05:07.360
Yes?
00:05:07.360 --> 00:05:07.759
Right.
00:05:07.759 --> 00:05:14.800
So all of those requirements are going to kick in at the 67% demolition threshold.
00:05:14.800 --> 00:05:29.680
I understand that you all will do a meeting with folks that sometimes you meet with homeowners or property owners or the contractor to talk about this 67% or to talk about the need for a demolition permit.
00:05:29.680 --> 00:05:32.639
Talk to us a little bit about how those meetings happen.
00:05:32.959 --> 00:05:33.279
Okay.
00:05:33.279 --> 00:05:41.920
So your plan reviewer, as he is reviewing your plans, if he determines, he or she determines the need for a meeting.
00:05:41.920 --> 00:05:42.399
Okay.
00:05:42.399 --> 00:05:54.160
Okay, for a demolition meeting, um, they will contact you usually through the comments on the plans that are that are sent back, stating that a meeting is needed.
00:05:54.319 --> 00:05:54.639
Yes.
00:05:54.959 --> 00:05:59.519
Now, it is definitely needed at that 67% threshold.
00:05:59.680 --> 00:06:00.079
Yes.
00:06:00.319 --> 00:06:10.480
But also, just to head off any problems, around 60%, when we start seeing the demolition getting up to 60%, okay, we're going to want to have a meeting with you.
00:06:10.720 --> 00:06:10.959
Okay.
00:06:11.120 --> 00:06:11.360
Okay.
00:06:11.360 --> 00:06:19.759
We're going to want you to understand and and be clear that that 67% is not negotiable.
00:06:19.759 --> 00:06:27.199
That if you if you happen to have an accident um on the on the what you're planning on leaving, that 7%.
00:06:27.199 --> 00:06:39.600
If you happen to go past that 67% from 60 to 67 and accidentally back a skid loader into a wall or find um termite damage in a wall that, oops, you know.
00:06:39.839 --> 00:06:40.319
Yes.
00:06:40.800 --> 00:06:42.160
That's a new home at that point.
00:06:42.160 --> 00:06:44.959
67% is a hard line in the sand.
00:06:45.279 --> 00:06:52.079
So if you find problems with other walls, you find problems with the other 33%, it can kick you into, or it can.
00:06:52.079 --> 00:06:53.439
I can't do the math.
00:06:53.439 --> 00:07:02.480
The other 40%, it can kick you into needing a demolition permit and needing to have your home considered a new home.
00:07:02.800 --> 00:07:03.519
That is correct.
00:07:03.519 --> 00:07:03.920
Yes.
00:07:04.399 --> 00:07:04.720
Okay.
00:07:04.720 --> 00:07:15.120
One of the things that we get asked in customer support about demolition, and I think one of the things that people are concerned about is impact taxes.
00:07:15.120 --> 00:07:19.920
If it's considered a new home, am I now going to pay impact taxes?
00:07:19.920 --> 00:07:25.759
And I think it's important for folks to note that demolitions are exempt from impact taxes.
00:07:25.759 --> 00:07:31.040
So if you are demolishing and you rebuild, then you don't have to pay impact taxes.
00:07:31.040 --> 00:07:32.480
They're waived at that point.
00:07:32.480 --> 00:07:39.519
So even if it's 67%, not 100%, as long as you're rebuilding on that spot, you don't have to pay impact taxes.
00:07:39.759 --> 00:07:42.000
Is there a time frame that that's applicable to?
00:07:42.319 --> 00:07:42.959
There is a time frame.
00:07:42.959 --> 00:07:44.399
It's four years.
00:07:44.399 --> 00:07:44.959
Okay.
00:07:44.959 --> 00:07:55.279
Um, and generally, if someone is 100% demolishing, then they may have that time to reconsider what they're going to rebuild.
00:07:55.279 --> 00:07:59.519
But if you're leaving 67%, you're not going to leave 33% of your house, right?
00:07:59.519 --> 00:08:01.040
It's not going to be sitting around for long.
00:08:01.040 --> 00:08:01.519
Right.
00:08:01.519 --> 00:08:04.240
It's not going to be hopefully it's not going to be sitting around for four years.
00:08:04.240 --> 00:08:05.839
Right.
00:08:05.839 --> 00:08:06.319
Okay.
00:08:06.319 --> 00:08:09.279
I know folks can do pre-design consultations.
00:08:09.279 --> 00:08:11.759
We have residential pre-design consultations.
00:08:11.759 --> 00:08:15.920
So this is certainly something that can be discussed at that point, too.
00:08:15.920 --> 00:08:20.639
You don't have to wait for the plan reviewer to give you a note on the plane.
00:08:20.959 --> 00:08:21.360
Right, right.
00:08:21.360 --> 00:08:25.839
Well, most likely in the pre-design, you that will be discussed.
00:08:25.839 --> 00:08:34.399
If um if we see that what you are proposing is getting close to that limit, it will the subject will be brought up.
00:08:34.399 --> 00:08:34.799
Okay.
00:08:34.799 --> 00:08:36.480
And you will be informed at that point.
00:08:36.960 --> 00:08:41.360
So you guys are paying attention to the plans and and how close I may be getting to that threshold.
00:08:41.360 --> 00:08:42.240
That's good to know.
00:08:42.240 --> 00:08:45.440
Where can I find information about this?
00:08:45.759 --> 00:08:46.080
Okay.
00:08:46.080 --> 00:08:48.080
Um on the DPS website.
00:08:48.080 --> 00:08:48.320
Okay.
00:08:48.320 --> 00:08:53.759
Um, we have put together a guideline for residential partial demolition.
00:08:53.759 --> 00:08:54.240
Okay.
00:08:54.240 --> 00:08:54.799
Okay.
00:08:54.799 --> 00:09:01.200
Um, I we recommend anybody who is um considering a project of this scope.
00:09:01.200 --> 00:09:04.480
Okay, do your homework, um, read this thoroughly.
00:09:04.480 --> 00:09:05.919
There's lots of good information, right?
00:09:05.919 --> 00:09:14.240
Um, you know, it's it's not just about leaving the walls, it's also about leaving the supporting structure under the walls.
00:09:14.480 --> 00:09:15.360
That's that's important.
00:09:15.440 --> 00:09:23.600
Yeah, a lot of times we see people try to take off portions of the supporting floor system.
00:09:23.759 --> 00:09:24.240
Yes.
00:09:24.480 --> 00:09:30.000
You've got to keep the foundation, you've got to keep the floor system supporting those walls intact.
00:09:30.000 --> 00:09:30.480
Okay.
00:09:30.480 --> 00:09:32.559
You can't alter those.
00:09:32.559 --> 00:09:34.879
That's all part of the structure.
00:09:35.200 --> 00:09:38.639
So if I'm removing the support of that wall, it's just like removing that wall.
00:09:38.960 --> 00:09:42.399
I mean, we've got some pictures of people hanging walls up in the air with a rope.
00:09:42.399 --> 00:09:42.720
Oh.
00:09:42.720 --> 00:09:44.480
And yeah.
00:09:46.080 --> 00:09:46.399
Okay.
00:09:46.399 --> 00:09:48.960
Well, that's a rope house I want to live in.
00:09:49.279 --> 00:09:49.759
Right.
00:09:50.080 --> 00:09:56.320
Um, we did a podcast recently about homeowners acting as their own contractor.
00:09:56.320 --> 00:09:59.679
My brothers and I can swing a mean sledgehammer.
00:09:59.679 --> 00:10:02.399
Should we be doing our own demolition?
00:10:02.399 --> 00:10:05.759
Should is that something that's best done by a contractor?
00:10:06.559 --> 00:10:09.200
You have the ability to do that.
00:10:09.440 --> 00:10:09.679
Okay.
00:10:09.840 --> 00:10:10.080
Okay.
00:10:10.080 --> 00:10:12.879
The county allows you, affords you that ability.
00:10:13.120 --> 00:10:13.360
Okay.
00:10:13.600 --> 00:10:21.840
If, but I would caution you, if you are capable, if you have the skill set, then you know that's something you can consider.
00:10:21.840 --> 00:10:29.279
If you do not have the skill set to tackle a project like this, um, it may be best to leave it to the professionals.
00:10:29.600 --> 00:10:29.919
Okay.
00:10:30.080 --> 00:10:30.240
Okay.
00:10:30.480 --> 00:10:31.679
That's good advice.
00:10:31.679 --> 00:10:40.080
I'm going to back up a little bit and talk about the meeting again, which I think is very important for folks to keep in mind who attends those meetings.
00:10:40.080 --> 00:10:43.039
Let's first talk about the pre-design consultation.
00:10:43.039 --> 00:10:44.799
Residential pre-design meeting.
00:10:44.799 --> 00:10:46.080
Who attends those meetings?
00:10:46.399 --> 00:10:48.960
Well, as an applicant, you have a project in mind.
00:10:48.960 --> 00:10:51.840
You're not really sure how you want to go, you have some questions about it.
00:10:51.840 --> 00:10:54.559
You schedule a meeting with us, okay?
00:10:54.559 --> 00:11:08.559
Um typically it's one of our plan reviewers or our residential um plan review manager is in that meeting to address anything specific to residential and any code questions.
00:11:08.559 --> 00:11:14.000
Um, I believe that zoning can be included, well and septic can be included in that meeting.
00:11:14.000 --> 00:11:18.399
It all depends on what's all relative to to the to the project itself.
00:11:18.639 --> 00:11:23.519
Now the demolition meeting specifically, who attends that meeting or who's involved in that?
00:11:23.840 --> 00:11:28.240
We will want to see um the obviously the owner of the meeting.
00:11:28.240 --> 00:11:30.960
Um I'm sorry, the owner of the property.
00:11:31.200 --> 00:11:31.440
Okay.
00:11:31.840 --> 00:11:39.759
Um we want included in that because ultimately he is responsible or they are responsible for the property itself.
00:11:39.759 --> 00:11:44.240
So we want the owner, we want the contractor because he's going to be doing the work.
00:11:44.240 --> 00:11:44.960
Okay.
00:11:44.960 --> 00:11:58.879
We want them to understand you know the parameters of the requirements, yes, and the you know, the limitations as far as where the bounds of where they need to stay within that scope.
00:11:59.200 --> 00:11:59.519
Okay.
00:11:59.679 --> 00:12:00.000
Okay.
00:12:00.000 --> 00:12:03.279
So basically those are the two main ones.
00:12:03.279 --> 00:12:09.600
Um ... possibly the architect um or engineer, yes, depending on the scope of work.
00:12:09.840 --> 00:12:10.080
Okay.
00:12:10.240 --> 00:12:10.960
So yeah.
00:12:11.360 --> 00:12:12.639
Are those meetings virtual?
00:12:12.639 --> 00:12:13.840
Are they in person?
00:12:14.720 --> 00:12:16.480
Most likely and typically virtual.
00:12:16.480 --> 00:12:16.960
Okay.
00:12:16.960 --> 00:12:21.279
Um we um makes things easier, keeps the environment cleaner.
00:12:21.279 --> 00:12:29.279
But if you um app uh uh want to have a face-to-face meeting, we can certainly accommodate you there.
00:12:29.279 --> 00:12:29.759
Okay.
00:12:29.759 --> 00:12:35.360
Um sometimes that is best to meet face to face, but um virtually is is good.
00:12:35.360 --> 00:12:36.399
It's fine as well.
00:12:36.559 --> 00:12:39.360
And the pre-design meetings are all done virtually, yes.
00:12:39.360 --> 00:12:39.840
Okay.
00:12:39.840 --> 00:12:40.480
Yes.
00:12:40.480 --> 00:12:49.360
As we talked about, Richard, some of these permits are in homeowners' names or they're in LLC names who are the property owners.
00:12:49.360 --> 00:12:52.240
And we talked about that on another podcast.
00:12:52.240 --> 00:13:00.000
But there's one thing that folks need to remember when it's a new home, and that's the Office of Consumer Protection.
00:13:00.000 --> 00:13:10.559
If it is a new home, then the applicant must be registered as a new home builder with Montgomery County Office of Consumer Protection.
00:13:10.559 --> 00:13:12.399
And that includes homeowners, yes?
00:13:12.639 --> 00:13:13.279
Correct, yes.
00:13:14.080 --> 00:13:20.159
So the homeowner would have to have a waiver or a permission from OCP to be able to build this new home.
00:13:20.480 --> 00:13:23.200
I believe it's a it's actually a builder's license from OCP.
00:13:23.200 --> 00:13:24.159
Yes, it is.
00:13:24.159 --> 00:13:25.360
Recall correctly.
00:13:25.360 --> 00:13:30.960
So yes, they will need to register with OCP and have a builder's
license from from them.
00:13:30.960 --> 00:13:34.960
Even homeowners, not just contractors, even homeowners.
00:13:34.960 --> 00:13:35.440
Right.
00:13:35.440 --> 00:13:41.679
If it's a homeowner that is attempting or tackling this project, then yes, they themselves will need this.
00:13:42.000 --> 00:13:49.440
So they're knocking down 40% of the walls, it's still an addition or an alteration, or an addition and an alteration.
00:13:49.440 --> 00:13:55.600
If they're knocking down 50% of the walls or 50% of the structure, they're still good.
00:13:55.600 --> 00:13:56.480
They're still good.
00:13:56.480 --> 00:13:59.200
It's when they reach what's the golden number?
00:13:59.679 --> 00:14:00.320
67%.
00:14:00.320 --> 00:14:01.039
Okay.
00:14:01.039 --> 00:14:04.240
And again, we're going to be talking to you as you get close to that.
00:14:04.240 --> 00:14:09.360
We're going to start talking to you at 60% or even less, maybe even after 50%.
00:14:09.360 --> 00:14:10.080
Okay.
00:14:10.080 --> 00:14:12.960
So, yeah, there will be conversations had.
00:14:12.960 --> 00:14:17.200
Um, so let me talk for a minute about what is an addition.
00:14:17.519 --> 00:14:17.759
Okay.
00:14:18.159 --> 00:14:20.320
What what are the differences here in permits?
00:14:20.320 --> 00:14:26.159
Uh, an addition is if you are actually adding roof space to your house.
00:14:27.120 --> 00:14:27.279
Oh, that's important, roof space. Okay.
00:14:27.519 --> 00:14:27.679
Okay.
00:14:27.679 --> 00:14:31.120
New roof areas, new floor space.
00:14:31.519 --> 00:14:31.759
O kay.
00:14:32.320 --> 00:14:37.840
An alteration is if you are taking an existing space in your home.
00:14:38.080 --> 00:14:38.399
Yes.
00:14:38.559 --> 00:14:40.639
Like, for example, let's say a carport.
00:14:40.720 --> 00:14:40.879
Yes.
00:14:41.120 --> 00:14:43.440
You have a carport, it's got a roof over it, no walls.
00:14:43.440 --> 00:14:46.000
You want to make it a garage and close it, okay?
00:14:46.000 --> 00:14:47.200
That's an alteration.
00:14:47.360 --> 00:14:47.679
Okay.
00:14:47.919 --> 00:14:52.320
You want to take that carport, you actually want to make it uh a new room, make it a family room.
00:14:52.480 --> 00:14:52.720
Okay.
00:14:52.799 --> 00:14:53.039
Okay.
00:14:53.039 --> 00:14:54.159
That's still an alteration.
00:14:54.320 --> 00:14:54.559
Okay.
00:14:54.799 --> 00:14:56.240
Because it's got a roof over it.
00:14:56.240 --> 00:14:56.639
Okay.
00:14:56.639 --> 00:15:03.279
So that that that's that's an alteration, and that's the uh definition of addition there.
00:15:03.600 --> 00:15:03.840
Thank you.
00:15:03.840 --> 00:15:05.440
That's that's helpful to know.
00:15:05.440 --> 00:15:06.399
What else?
00:15:06.399 --> 00:15:07.120
What else?
00:15:07.120 --> 00:15:16.399
If there's one thing that folks need to walk away or remember about this podcast, what's the one piece of advice or information that you want us to remember?
00:15:16.720 --> 00:15:19.039
It would be that 67% threshold.
00:15:19.039 --> 00:15:19.679
Okay.
00:15:19.679 --> 00:15:20.240
Okay.
00:15:20.240 --> 00:15:23.679
That is where your headaches are going to come from.
00:15:23.679 --> 00:15:24.000
Okay.
00:15:24.000 --> 00:15:39.279
If you're trying to maintain an additional status with your permit, um if, like I said mentioned earlier, if accidents happen, we want you to understand the ramifications of that accident.
00:15:39.279 --> 00:15:43.360
You don't get a do-over, you can't patch the wall back up and tack it back up.
00:15:43.759 --> 00:15:44.000
Yes.
00:15:44.000 --> 00:15:46.159
No, it's down at that point.
00:15:46.159 --> 00:15:46.960
Right.
00:15:46.960 --> 00:15:47.440
All right.
00:15:47.679 --> 00:15:48.799
And it is a new home.
00:15:49.039 --> 00:15:50.559
And it is a new home.
00:15:50.559 --> 00:15:53.759
Thank you, Richard, for joining us on the podcast today.
00:15:53.759 --> 00:15:56.559
And thank you, our listeners, for tuning in.
00:15:56.559 --> 00:16:12.159
If you have questions you'd like to see answered on our podcast, or you have a suggestion for a topic you'd like to hear us talk about, please let us know at dps.podcast at MontgomeryCountymd.gov.
00:16:12.159 --> 00:16:25.039
And remember, all of this information is available on the DPS main website at MontgomeryCountymd.gov forward slash DPS.
00:16:25.039 --> 00:16:27.200
Again, thank you for tuning in.
00:16:27.200 --> 00:16:29.279
I'm Gail Lucas, your host.
00:16:29.279 --> 00:16:33.279
Remember, DPS is your project partner.
00:16:36.159 --> 00:16:43.919
This podcast is brought to you by County Cable Montgomery, your source for news and information from the Montgomery County government.
00:16:43.919 --> 00:16:50.879
Connect with us via cable, Facebook, Instagram, or YouTube by searching for County Cable MOCO.