Morning, Shane.
00:00:05.599 --> 00:00:06.320
Good morning, Neil.
00:00:06.559 --> 00:00:10.960
So remember when we first met, was on that project in Shoreline.
00:00:11.119 --> 00:00:18.239
You were doing the dirt, we were doing the utilities, and I come on site and there's this giant hole opened up on the project, right?
00:00:18.320 --> 00:00:21.359
And you're pushing dirt, garbage, loading that out.
00:00:21.600 --> 00:00:28.160
Long story short, there were a couple of boring test pits, but they didn't do any where the building was going.
00:00:28.320 --> 00:00:28.719
Absolutely.
00:00:29.039 --> 00:00:32.240
Come to find out later, that used to be like the neighborhood dump site.
00:00:32.399 --> 00:00:34.960
For years they were dumping everything in that hole.
00:00:35.759 --> 00:00:38.000
Cost the owners thousands of dollars.
00:00:38.320 --> 00:00:38.880
Thousands.
00:00:38.960 --> 00:00:43.759
I I can't remember what it was, but I think it was somewhere close to 80 grand of dump fees.
00:00:44.000 --> 00:00:44.240
Right.
00:00:44.399 --> 00:00:52.479
So had had they done a couple more bore pets or test holes, they that situation wouldn't have changed, but at least they could have budgeted for that, right?
00:00:52.640 --> 00:00:53.039
Absolutely.
00:00:53.200 --> 00:00:55.759
Unforeseen conditions like that bite you every time.
00:00:56.000 --> 00:01:03.600
Welcome to the dirt with Alpine Civil Consulting, the podcast where we dig into the people, projects, and problems that shape the world beneath our feet.
00:01:03.679 --> 00:01:04.719
I'm Neil Tastad.
00:01:04.959 --> 00:01:06.159
And I'm Shane Crosby.
00:01:06.239 --> 00:01:11.120
Between us, we've spent decades in heavy civil construction solving problems that most people never see.
00:01:11.280 --> 00:01:20.159
This podcast is for contractors, developers, engineers, municipalities, architects, and anyone curious about what really goes on in the building, a successful project.
00:01:20.480 --> 00:01:26.799
If you ever wondered why projects go over budget, get delayed, or run into unexpected issues, you're in the right place.
00:01:27.040 --> 00:01:27.760
Let's dig in.
00:01:28.079 --> 00:01:34.799
So as we discussed earlier about a particular project that Neil and I met on, a couple of things were missed on that project, as Neil touched on.
00:01:35.040 --> 00:01:38.959
Lack of specific bore pits in the location of the building, which bit everybody.
00:01:39.120 --> 00:01:41.359
Time, money, which is a headache.
00:01:41.519 --> 00:01:48.640
Most of these projects go over bid because of these missed opportunities that could have been caught on day one with a little bit more constructibility done.
00:01:48.719 --> 00:01:49.680
Don't you agree, Neil?
00:01:49.920 --> 00:01:50.159
I do.
00:01:50.400 --> 00:01:54.079
So why do over 40% of civil projects go over budget?
00:01:54.239 --> 00:01:57.200
Usually because the right people aren't in the room
Load full transcript
on day one.
00:01:57.439 --> 00:01:57.920
You're right.
00:01:58.079 --> 00:02:04.799
And statistics say 40%, but you and I know with the experience that we have that almost every project has the same hiccup.
00:02:04.959 --> 00:02:07.599
We're now digging ground that's been dug and used prior.
00:02:07.760 --> 00:02:09.520
The days of open ground is done.
00:02:09.680 --> 00:02:14.800
Lack of constructibility on these projects today cost everybody contractor, developer, owner, everybody.
00:02:14.960 --> 00:02:22.000
So not catching these things up front, not overlaying the project to see what was there before hurts the schedule and cost everybody time and money.
00:02:22.240 --> 00:02:26.319
Yeah, it's it's not necessarily that the costs aren't there for the project.
00:02:26.400 --> 00:02:28.159
They're just not being budgeted for, right?
00:02:28.319 --> 00:02:28.960
Absolutely.
00:02:29.199 --> 00:02:32.719
Some of the stuff can be caught just in the design phase of the project.
00:02:32.879 --> 00:02:38.800
Not having a civil consultant with boots on the ground experience on a project from day one hurts the whole project as a whole.
00:02:39.039 --> 00:02:41.840
So, Shane, what do you what do you mean when you say boots on the ground experience?
00:02:42.159 --> 00:02:47.439
Well, Neil, you and I have over 60 years of experience, and we've seen, we don't know everything, but we've seen a lot.
00:02:47.680 --> 00:02:50.879
We have you know, and and the boots on the ground experience is just that.
00:02:50.960 --> 00:02:57.120
We've been in the trenches, we've dealt with these problems on a day-to-day basis on every single project we've done.
00:02:57.280 --> 00:03:04.400
You and I have been working together now over 15 years, working up to 17 years, I think, in a few or 16 years, excuse me, in the next couple of months.
00:03:04.560 --> 00:03:06.479
Name one project where this wasn't an issue.
00:03:06.639 --> 00:03:08.319
Yeah, it's it's every project.
00:03:08.560 --> 00:03:09.599
Recently had a project.
00:03:09.680 --> 00:03:11.840
We got the job, we went out and we looked at it.
00:03:11.919 --> 00:03:16.479
And day one, with an approved set of plans, we already knew just looking at the job, it wasn't going to work.
00:03:16.639 --> 00:03:17.120
Why was that?
00:03:17.280 --> 00:03:17.680
Why was it?
00:03:17.840 --> 00:03:19.439
No boots on the background experience.
00:03:19.599 --> 00:03:24.560
Civil engineer did a fantastic job designing the project, but didn't know overlay what was already in the ground.
00:03:24.800 --> 00:03:27.280
Yeah, so so how does that happen?
00:03:27.520 --> 00:03:31.520
So lack of what as built, um, locates?
00:03:32.159 --> 00:03:33.120
A couple of things, right?
00:03:33.280 --> 00:03:38.080
Lack of experience in the field, lack of knowledge of the utilities that are already in the ground.
00:03:38.240 --> 00:03:45.039
In the designing process, if they're not doing a locate on the project to see what's
existing in the ground, how can they actually design a project?
00:03:45.360 --> 00:03:45.599
Right.
00:03:45.680 --> 00:03:49.599
So that goes back to the start of the whole process.
00:03:49.759 --> 00:03:51.199
So how do how does this start?
00:03:51.360 --> 00:03:55.680
So it starts with what a concept, a design, starts with a budget.
00:03:55.840 --> 00:04:02.639
Maybe the architects, engineers are given a budget and they're trying to fit this design within that budget, right?
00:04:02.719 --> 00:04:03.599
I'm I'm guessing.
00:04:03.840 --> 00:04:04.080
Yes.
00:04:04.319 --> 00:04:10.400
Well, but it brings to mind one of the biggest pet peeves in this vendor for me, which is low bid gets the job, right?
00:04:10.560 --> 00:04:17.519
That knows every faculty of the job from engineering to general to the dirt contractor doing the work, right?
00:04:17.759 --> 00:04:29.519
Right, but but let's back up to the the design stage where if if you have a limited budget to do the design, you're gonna get, are you gonna go out there and just go off as builds?
00:04:29.600 --> 00:04:31.600
Are you even gonna have as builds provided?
00:04:31.680 --> 00:04:33.199
Sometimes they're not provided, right?
00:04:33.279 --> 00:04:36.399
If you're doing uh some road work, how about do locates?
00:04:36.639 --> 00:04:37.680
Wow, that was a concept.
00:04:38.000 --> 00:04:41.519
Locates and then hire a contractor to go out and potholes.
00:04:41.600 --> 00:04:47.199
So you got invert elevations of utilities, you know what's in the ground, then you can design the project.
00:04:47.360 --> 00:04:48.079
Yeah, absolutely.
00:04:48.160 --> 00:05:01.120
I mean, it wasn't very long ago that you and I were involved in a project, and again, I'm not gonna mention names or locations, but day one we walk out on the project and they had all these saved trees, and the very first tree I looked at that was supposed to be a saved tree, was 45-degree angle over the top of the project.
00:05:01.199 --> 00:05:01.279
Right.
00:05:01.439 --> 00:05:03.600
You and I looked at each other, we're like, well, that's not gonna happen.
00:05:03.680 --> 00:05:08.240
The engineer designed it off of Google Earth, no boots on the ground, nobody walked out there and looked at it.
00:05:08.399 --> 00:05:09.920
But again, why why is that happening?
00:05:10.319 --> 00:05:12.800
Lack of experience, maybe the industry's changing.
00:05:12.879 --> 00:05:14.000
I I'm not exactly sure.
00:05:14.160 --> 00:05:17.519
This is this is the frustration I think every contractor has right now.
00:05:17.680 --> 00:05:23.040
Actually, maybe not the contractor as much as the owner developer, because they're now gonna get hit with the almighty extra.
00:05:23.279 --> 00:05:23.439
Right.
00:05:23.600 --> 00:05:26.000
Which unfortunately in our industry becomes the norm.
00:05:26.240 --> 00:05:39.839
With the consultants such as Alpine Civil Consulting, allow us to do a deep dive onto the project, say thousands of dollars by spending pennies up front with somebody to take a look at the project, see if their design, their dream is even possible.
00:05:40.079 --> 00:05:40.959
If it's constructible.
00:05:41.199 --> 00:05:41.839
If it's constructible.
00:05:41.920 --> 00:05:42.959
I mean, it wasn't very long ago.
00:05:43.040 --> 00:05:49.759
I had a conversation with an engineer who said, Shane, I'm I want imagine I'm building this house and I want you to build the house the way I designed it.
00:05:49.839 --> 00:05:51.600
I want to build the house the way you designed it.
00:05:51.680 --> 00:05:53.279
I just got to make sure it's gonna stand up.
00:05:53.519 --> 00:05:56.240
Well, and it's gotta fit within the project.
00:05:56.560 --> 00:05:56.879
Yeah, yeah.
00:05:57.120 --> 00:06:02.480
And it's it's sometimes frustrating that that we we see this time and time again, almost every single project.
00:06:02.720 --> 00:06:13.600
Yeah, if we could get involved early and and lay out the the issues that we see, by the time it goes to the bid build process, hopefully a lot of these issues are flushed out.
00:06:13.759 --> 00:06:20.319
Not that the costs are gonna go away, but at least the owner has an idea of hey, this this is a more realistic budget for my project.
00:06:20.480 --> 00:06:21.360
Yes, exactly.
00:06:21.519 --> 00:06:29.439
Every time we see here's the engineer's estimate on a project, but if they haven't done a complete constructability study on the project prior to designing it, that budget's kind of not there.
00:06:29.519 --> 00:06:31.759
Yeah, it kind of leaves an open door for these changes.
00:06:32.000 --> 00:06:48.800
And then what happens during the course of the the project, Lil Bid gets gets the work right, and then it's change order, change order, change order, which the owners the project, donors getting hit, the general contractors getting hit, the subcontractors are getting hit, everyone down the line is being asked to participate in the costs.
00:06:49.120 --> 00:06:51.759
The one word we can't stand is the contractor, participate.
00:06:52.160 --> 00:06:58.240
Especially when when we don't have any say in the upfront design constructibility of that project.
00:06:58.480 --> 00:07:01.519
Or in the back end, we don't get any profit when the project's done.
00:07:01.680 --> 00:07:04.959
Our profit's in the design we do, the work we do, the job that was bid.
00:07:05.199 --> 00:07:08.319
Yeah, the quicker we can get in and out of a project, the more profitable it is.
00:07:08.639 --> 00:07:09.360
Way more profitable.
00:07:09.439 --> 00:07:17.519
Everybody wants to hang their hat on change orders and TM stuff, but at the end of the day, the paperwork mill that's got to go through the office eats that up alive.
00:07:17.680 --> 00:07:18.319
There's no profit.
00:07:18.480 --> 00:07:18.720
No.
00:07:18.959 --> 00:07:22.480
So Shane, we talked about where the money is being spent on these projects.
00:07:22.720 --> 00:07:34.000
Seems like they're being spent starting at the bid-build process towards the end of the project or middle start, what have you, in change orders, that money should be shifted towards the beginning of the project.
00:07:34.079 --> 00:07:38.160
So is it ever too early to get a civil consultant involved in these?
00:07:38.399 --> 00:07:42.000
It's never too early to get a company like Alpine Civil Consulting in there.
00:07:42.160 --> 00:07:43.120
The earlier the better.
00:07:43.199 --> 00:07:47.680
The faster we can get in there to catch it and see design and help out where we see the need.
00:07:47.920 --> 00:08:02.160
So in our next episode, we'll deconstruct a constructability study that we put together on a local project where we go into more specifics on what we found outside of the plans, outside of the geotech reports.
00:08:02.319 --> 00:08:07.680
We go into the permitting or extra permitting that was necessary for this project.
00:08:07.759 --> 00:08:16.079
Um, and then as well as the I shouldn't say extra cost, but the cost that wouldn't have been identified had we not done this report.
00:08:16.319 --> 00:08:17.040
Yes, exactly.
00:08:17.199 --> 00:08:19.759
So until next time, I'm Jayne Crosby.
00:08:19.839 --> 00:08:20.959
I'm Neil Tastad.
00:08:21.040 --> 00:08:21.839
This is the dirt.
00:08:22.000 --> 00:08:23.040
Keep digging.
00:08:23.519 --> 00:08:34.639
And just a quick reminder if you have any questions or concerns, you can reach out to us on our website or email our team and follow us on our LinkedIn, Instagram, and other social media platforms.